JustGlad Oil & Gas Company Limited
Projects & Case Studies

Project experience with context, scope and outcomes.

Selected references demonstrate JustGlad’s exposure across refinery support, workforce services, civil works and specialist procurement.

Case Study

Dangote Refinery — Onshore Pipe Laying

Execute underground sewer and gravity-line works within the Dangote Refinery project environment, incorporating manholes, junction chambers and associated underground piping infrastructure.

Completed Project
Project Scope
Construction and installation of manholes and junction chambers in accordance with client/main-contractor drawings and specifications
Earth excavation for manholes and gravity-line installation
Laying and installation of 12-inch, 10-inch and 6-inch UPVC pipes
Grouting and benching of manholes
Gravity testing of installed UPVC lines